release_schedule_in_2015
0.9.2 : “Spec vA Compliant + Spec vB Partial”
Type for Release : Minor release, Schedule Driven, PlugFest #3
Schedule (5 weeks ahead of QA completion) (cf. Original QA request is 6 weeks ahead of QA start)
6/22,
API freeze & Programmer’s guide freeze
7/17, Feature complete & Review Complete and make “0.9.2-RC1” release to QA
7/24, QA 1st round complete
8/03, 0.9.2-RC2 release to QA
8/06, QA 2nd round complete
8/10, Website Open
8/17 week, Plug Fest #3
0.9.3 : “Code Enhancement”
1.0.0 : “OIC Spec 1.0 Compliant release”
Type for Release : Major release, Feature Driven, PlugFest #4
Schedule (6 weeks ahead of QA completion) (cf. Original QA request is 6 weeks ahead of QA start)
08/28,
API freeze & Programmer’s guide freeze
09/21, Feature complete & Review Complete and make “1.0.0-RC1” release to QA
09/25, QA 1st round complete
09/29, Make “1.0.0-RC2” release to QA
10/02, QA 2nd round complete
10/05, Make “1.0.0-RC3” release to QA
10/09, QA 3rd round complete
10/12, Website Open
10/27~29, Plug Fest #4
release_schedule_in_2015.txt · Last modified: 2015/10/06 00:33 by June Young