0.9.2 : “Spec vA Compliant + Spec vB Partial”

  • Type for Release : Minor release, Schedule Driven, PlugFest #3
  • Schedule (5 weeks ahead of QA completion) (cf. Original QA request is 6 weeks ahead of QA start)
    • 6/22, API freeze & Programmer’s guide freeze
    • 7/17, Feature complete & Review Complete and make “0.9.2-RC1” release to QA
    • 7/24, QA 1st round complete
    • 8/03, 0.9.2-RC2 release to QA
    • 8/06, QA 2nd round complete
    • 8/10, Website Open
    • 8/17 week, Plug Fest #3

0.9.3 : “Code Enhancement”

  • Type for Release : Minor release, Schedule Driven
  • Proposal : Skip 0.9.3

1.0.0 : “OIC Spec 1.0 Compliant release”

  • Type for Release : Major release, Feature Driven, PlugFest #4
  • Schedule (6 weeks ahead of QA completion) (cf. Original QA request is 6 weeks ahead of QA start)
    • 08/28, API freeze & Programmer’s guide freeze
    • 09/21, Feature complete & Review Complete and make “1.0.0-RC1” release to QA
    • 09/25, QA 1st round complete
    • 09/29, Make “1.0.0-RC2” release to QA
    • 10/02, QA 2nd round complete
    • 10/05, Make “1.0.0-RC3” release to QA
    • 10/09, QA 3rd round complete
    • 10/12, Website Open
    • 10/27~29, Plug Fest #4